Somaya Solar Solutions Limited is an EPC contractor for PM-KUSUM solar plants. This page sets out how the scheme works for land and pumps in Ladakh and what we do on such a project.

What PM-KUSUM covers

PM-KUSUM is a central government scheme of the Ministry of New and Renewable Energy, run in each state by state implementing agencies. Capacity is allotted to states on demand. The Ministry told the Lok Sabha on 29 July 2026 that the scheme's timeline is extended to 31 March 2027 for all components.

  • Component A: decentralised solar plants of up to 2 MW on farmers' land.
  • Component B: solar pumps for agriculture.
  • Component C: solarisation of grid-connected agriculture pumps, including feeder-level solarisation.

Who runs PM-KUSUM in Ladakh

In Ladakh, LREDA takes farmers' applications for Component B in Leh district. The Ministry of New and Renewable Energy reports no capacity under Component A and nothing under Component C. We found no official source on who runs Components A and C in Ladakh, or on any tariff the regulator fixed for them.

  • Progress reported to the Lok Sabha up to 30 June 2026: 265 solar pumps installed under Component B, all in 2025-26. Nothing is shown under Component A or C.
  • For Component B in Leh district, an MNRE flowchart says the farmer submits the application form at the LREDA office at the Energy Park in Leh; the application fee is ₹20 per form. The flowchart file is dated 28 October 2022.
  • The central government has extended the scheme to 31 March 2027 for all components.

What Somaya Solar does on a PM-KUSUM plant

Somaya Solar works as the EPC contractor for the farmer, developer or group that holds the allocation. It does not allot capacity or decide subsidy.

  • Site check of the land and its distance from the substation
  • Plant design and equipment supply
  • Installation, testing and commissioning
  • The line to the substation and coordination with the electricity supplier
  • Support with the documents the implementing agency asks for

More detail: PM-KUSUM across India.

Questions about solar projects in Ladakh

Who do I apply to for PM-KUSUM in Ladakh?

In Ladakh, LREDA takes farmers' applications for Component B in Leh district. The Ministry of New and Renewable Energy reports no capacity under Component A and nothing under Component C. We found no official source on who runs Components A and C in Ladakh, or on any tariff the regulator fixed for them.

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Ladakh

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 18 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.