Somaya Solar Solutions Limited builds ground-mounted solar power plants in Puducherry for businesses that want their own power and for landowners and developers who sell power to the grid.

State policy and open access in Puducherry

We could not confirm a current Puducherry solar policy as of November 2026. The Policies page of the Puducherry government portal (updated 12 November 2026) lists no solar or renewable energy policy. A Puducherry Solar Energy Policy of 2015-16 is reported on the REAP website, but that site's security certificate fails, so we could not open it to read its term. Rooftop solar follows the JERC net metering regulations, as the Electricity Department's guidelines say. National schemes (PM Surya Ghar for homes, PM-KUSUM for farmers) apply.

  • The Electricity Department's revised rooftop guidelines (January 2024) rest on the JERC (Solar PV Grid Interactive System based on Net Metering) Regulations, 2019.

JERC brought green energy open access into its Connectivity and Open Access Regulations, 2017 through the Third Amendment of 2024, published in the Gazette of India on 19 September 2024. A consumer in Puducherry with a contract demand or sanctioned load of 100 kW or more can take renewable power through open access. The 100 kW can be one connection or several connections in the same electricity division.

  • Captive consumers have no load limit.
  • Banking is allowed within the month or billing cycle, up to 30% of the consumer's monthly consumption from the licensee. The banking charge is 8% of the banked energy, taken in units. Banked energy cannot be carried to the next month; unused energy lapses and the generator gets renewable energy certificates for it.
  • For 2026-27 the tariff order sets a cross-subsidy surcharge of ₹1.41 per unit at HT and ₹1.32 per unit at EHT, and an additional surcharge of ₹1.43 per unit. Neither surcharge applies to captive use.
  • The additional surcharge is not charged on green energy open access up to the contract demand if the consumer pays fixed charges to the licensee for it.
  • The wheeling charge for 2026-27 is ₹0.48 per unit at HT and ₹0.47 per unit at EHT.
  • The regulatory surcharge of 10% on energy and demand charges, in force from 1 October 2025, also applies to consumers using open access.
  • Standby charges for a green energy open access consumer may not be more than 25% of the energy charge of the consumer's tariff category.

What a ground-mounted project involves

A ground-mounted plant needs more groundwork than a rooftop one before any module is fixed.

  • Land check: title, slope, soil, drainage, access road and shading
  • Distance to the substation or connection point and the line needed to reach it
  • Layout, structure design and foundations for the soil
  • Supply, installation, testing and commissioning
  • Evacuation line, metering and connection approvals
  • Fencing, cleaning water and maintenance planning

More detail: Ground-Mounted Solar Plant across India.

Questions about solar projects in Puducherry

How much land does a solar plant need?

A fixed-tilt ground-mounted plant typically needs about 4 to 5 acres for each MW. The exact area depends on the module, the tilt and the shape of the plot.

Where is Somaya Solar based?

Somaya Solar Solutions Limited works from C-159, Bulandshahr Road Industrial Area, Ghaziabad, Uttar Pradesh.

What does Somaya Solar need to prepare a proposal?

Twelve months of electricity bills, the sanctioned load or contract demand, the roof or land details with photographs, and the plant size you have in mind if you have one.

Discuss a solar project in Puducherry

Send your electricity bills, sanctioned load and roof or land details, and we will reply with a first assessment.

Request a proposal

Email: info@somayasolar.com
Phone: +91-8700035846

Sources

Local rules and figures on this page were last checked on 19 November 2026. Rules and tariffs change; confirm the current position before you commit to a project.

Certificates & Recognition

Our certifications and recognitions reflect our focus on quality, safety, compliance, and responsible project execution across our solar operations.

Loading Image