Project Overview

Somaya Solar successfully executed a 3 MW rooftop solar project for Naini Papers Limited, a paper manufacturing facility located in Kashipur, Uttarakhand.
The project involved the supply, installation, testing, and commissioning of the rooftop solar system, along with five years of Operations & Maintenance (O&M) support to help maintain reliable long-term system performance.

Scope of Work

Somaya Solar was responsible for:

  • Supply of solar project equipment and components
  • Complete rooftop solar installation
  • Testing and commissioning of the solar power system
  • Project coordination and execution
  • Five years of Operations & Maintenance (O&M)

The Challenge

One of the key requirements of the project was its tight execution timeline. The complete 3 MW rooftop solar project had to be delivered within just two months.
For a project of this scale, meeting the deadline required careful planning, efficient resource allocation, and simultaneous execution across multiple work fronts.

Our Approach

To meet the demanding project schedule, Somaya Solar deployed multiple installation and commissioning (I&C) teams at the site.
Instead of following a completely sequential execution process, different teams worked in parallel across multiple project activities. This approach helped optimize the available time, maintain coordination between different stages of execution, and keep the project on schedule.
Through structured project management and coordinated on-site execution, the team successfully completed the project within the required two-month timeline.

Project Outcome

The 3 MW industrial rooftop solar project was successfully completed, tested, and commissioned and is currently operational.
The project demonstrates Somaya Solar’s capability to execute large-scale industrial solar EPC projects within challenging timelines, while managing supply, installation, commissioning, and long-term O&M under a unified project scope.

Project at a Glance

Project Parameter             

Details

Client

Naini Papers Limited

Industry

Paper Mill

Location

Kashipur, Uttarakhand

Solar Capacity

3 MW

Project Type

Rooftop Solar

Scope

Supply, Installation, Testing & Commissioning     

O&M Support

5 Years

Execution Timeline

2 Months

Current Status

Completed & Operational

Powering Industrial Operations with Solar

From engineering and project execution to commissioning and long-term O&M, Somaya Solar Solutions supports industries with end-to-end solar EPC capabilities. Our focus is on delivering solar projects that align with the site’s operational requirements, project timelines, and long-term energy goals.

Project Information

  • Category

    Industrial Rooftop Solar
  • Location

    Kashipur, Uttarakhand
  • Date

  • Capacity

    3 MW
Loading Image